Developer Schedule Health
A first-pass schedule-risk monitor built from DLD Projects and Developers open data. DPI consolidates verified project-owning legal entities and SPVs to the public-facing parent developer brand before comparison.
DLD project-status snapshot • 15 June 2026
Which active portfolios show schedule warnings?
| Parent developer | Active projects | End-date coverage | Past expected end | Schedule-warning rate |
|---|---|---|---|---|
| Emaar | 90 | 67 / 90 (74%) | 8 | 12% |
| DAMAC | 47 | 32 / 47 (68%) | 18 | 56% |
| Sobha | 18 | 9 / 18 (50%) | 0 | 0% |
| Danube | 17 | 9 / 17 (53%) | 4 | 44% |
| Binghatti | 16 | 12 / 16 (75%) | 9 | 75% |
Definition: “Past expected end” means a project was still marked
ACTIVE even though its registered expected end date was before the DLD snapshot date.
Projects without an end date are excluded from the warning-rate denominator.
Important: this is not an on-time delivery ranking and it is not a construction-quality score. Actual handover evidence and consistent building-quality coverage are required before DPI publishes those measures.
Important: this is not an on-time delivery ranking and it is not a construction-quality score. Actual handover evidence and consistent building-quality coverage are required before DPI publishes those measures.
Sources: Dubai Land Department Projects and Developers open datasets. Parent-brand normalisation is retained in DPI's methodology audit trail.